							AFFECTED AREAS:FEEDER 3-1MARIBULAN, SACI,VALENCIA,ALEGRIA, MINANGA, BUAYAN, ASINANFEEDER 3-2MUNICIPALITY OF ALABEL, MUNICIPALITY OF MALAPATANFEEDER 3-3SARANGANI AQUA RESOURCESREASON: SARI SUBSTATION PREVENTIVE MAINTENANCE, REPAIR OF LEAKING SECONDARY BUSHING AND INSTALLATION OF METERING CURRENT T...							
																					 Read More
						
								Dec
								04
								2017
							
							
																					
							Parts of Alabel and Malapatan are currently out of power since 1am due to defective recloser and current transformer serving SARI substation caused by heavy lightning occurence early dawn today.TSD personnel are doing repair works which is expected to be completed by 12nn. Thank you							
																					 Read More
						
								Dec
								02
								2017
							
							
																					
							Sari substation serving alabel and malapatan is currently out due to emergency maintenance activities. Oil leaking found from its transformer. Expected to be completed by 11am. Thank You.							
																					 Read More
						
								Dec
								01
								2017
							
							
																					
							Please be informed that there will be an emergency 1-HOUR shutdown today, December 1, 2017, 12:00 NN to 1PM affecting all areas covered by MAIN OFFICE SUBSSTATION to facilitate hot-spot correction for feeder's disconnection switch.Should there be interruptions outside the given schedule, please c...							
																					 Read More
						
								Nov
								29
								2017
							
							
																					
							Repair works for main office 35MVA substation is estimated at 80% completion. We hope to restore power within the next 3 hours.We again appeal for your kind understanding. Thank you.							
																					 Read More
						
								Nov
								29
								2017
							
							
																					
							Please be informed that areas covered by SOCOTECO II Main office 35MVA substation is currently on total blackout due to main breaker burnout at secondary side. Restoration going on and expected to last up to 12 midnight. Our technical personnel are trying their best for soonest completion of repa...							
																					 Read More
						
								Nov
								29
								2017
							
							
																					
							Main Office Substation repair works succesfully completed. All feeders are now energized.Thank you for bearing with us and we apologize for the inconveniece it may have caused.							